| Mar 2000 Present |
Licensing and Safety Manager, Idaho Spent Fuel
Project
Managed safety analysis and preparation of NRC license application for
spent fuel storage facility to be constructed in Idaho Falls. |
Feb 1998
Mar 2000 |
Licensing Engineer Consultant Robinson Nuclear
Plant
Assigned responsibility for preparation of Licensee Event Reports (LERs),
Notice of Enforcement Discretion (NOED), Technical Specification
Amendments, and NRC Violation Responses. |
Jan 1997
Dec 1997 |
Operations Consultant to Florida Power Corporation
(Crystal River Nuclear Plant)
Assigned lead responsibility for complete revision to all Abnormal
Operating procedures. |
Sept 1996
Jan 1997 |
Licensing Consultant to Portland General Electric
(Trojan Nuclear Plant)
Assigned responsibility for development of 10CFR71 license application
to allow shipment of the Trojan reactor vessel as a Type B package for
burial at U.S. Ecology waste site near Richland, Washington. |
Feb 1996
Mar 1996 |
Licensing Consultant to Portland General Electric
(Trojan Nuclear Plant)
Assigned responsibility for development of 10CFR72 license application
for an Independent Spent Fuel Storage Installation (ISFSI). |
May 1995
Nov 1995 |
Licensing Consultant to Portland General Electric
Trojan Nuclear Plant)
Assigned as Project Manager, ISFSI Licensing. |
Aug 1994
Jan 1995 |
Licensing Consultant to Portland General Electric
(Trojan Nuclear Plant)
Original assignment was development of Decommissioning Plan for
submittal to Nuclear Regulatory Commission. Primary area of
responsibility was development/authoring accident analysis. Upon
completion of Decommissioning Plan, was assigned to author 10CFR71
submittal to allow steam generators and pressurizer to be utilized as
self-contained shipping containers. In addition to authoring 10CFR71
application, I was responsible for identify design deficiencies that
allowed correction prior to submittal to NRC. As a result of the
thoroughness of the document, the NRC commented on the quality of the
submittal and granted approval in record time (approximately 6
months). |
Nov 1993
Mar 1994 |
Consultant to Washington Public Power Systems
(WNP-2)
Performed detailed review of Technical Specification Surveillance
requirements to ensure implementation by plant procedures. |
| August 1994January 1995 |
Licensing Consultant to Portland General Electric
(Trojan Nuclear Plant)
Developed Decommissioning Plan for submittal to Nuclear Regulatory
Commission (NRC). |
July 1993
Sept 1993 |
Licensing Consultant to Portland General Electric
(Trojan Nuclear Plant)
Development of Defueled Safety Analysis Report for Trojan Nuclear
Plant. Areas assigned for development were Site Characteristics,
Operations, and Accident Analysis. |
Jan 1993
July 1993 |
Consultant to Department of Energy
Responsibilities included review of DOE facility Safety Analysis
Reports to ensure compliance with DOE Orders, Code of Federal
Regulations, and other applicable statutes. |
Oct 1992
Dec 1992 |
Assigned as Senior Licensing Engineer
Duties included development of Technical Specification
Interpretations, Safety Evaluation reviews, and major update/revision
of the Final Safety Analysis Report. |
Nov 1991
Sep 1992 |
Licensing Consultant Nine Mile Point
Assigned as Senior Licensing Engineer. Duties included development of
Technical Specification Amendments, Waivers of Compliance, Technical
Specification Interpretations. |
June 1990
July 1991 |
Licensing/Engineering Consultant
Florida Power Corporation (Crystal River #3)
|
Aug 1982
Dec 1988 |
Nuclear Operations Superintendent/Technical
Advisor
Crystal River #3
Responsible for all operational aspects of the Crystal River Nuclear
generating facility. In charge of Licensed and Non-Licensed Operators
(approximately 74 personnel). |
Oct 1980
Aug 1982 |
Nuclear Results/Plant Engineer Crystal River #3
|